Re Straightline Construction Co Pty Ltd [2022] VSC 708 (18 November 2022); Application to set aside a statutory demand pursuant to s 459G of the Corporations Act 2001 (Cth) on grounds of genuine dispute, dispute as to the identity of the contracting parties
December 4, 2022
In Re Straightline Construction Co Pty Ltd [2022] VSC 708 the Supreme Court, per Gardiner AsJ, considered an application to set aside a statutory demand on the grounds that the applicant was not a party to the agreement giving rise to a liability which formed the basis of a statutory demand. This is quite a common issue where parties are involved in the building and construction industry. It is not uncommon for builders to work through multiple entities, many of whose names are quite similar. As this case demonstrates, it is not simply enough for the Applicant to allege that the wrong party was served with a demand as another entity was a party to the contract. As this case shows such a contention can be successfully challenged if the respondent has contemporaneous documentation and concessions by representatives of the applicant .
FACTS
On 9 December 2021, Hansen Yuncken Pty Ltd (‘Hansen Yuncken’), as head contractor, engaged Straightline Civil Pty Ltd (‘Straightline Civil’), as subcontractor, (‘the Hansen Yuncken Contract’) to carry out retention and foundation piling works as part of a large residential construction project at Bills Street, Hawthorn (‘the Project’) [6]
Straightline Construction’s evidence was that:
- it defined the issue as
[Straightline Construction] disputes that the debt claimed in the Statutory Demand is due and payable, by reason of there being a genuine dispute that the debt is owing as the Company is not the entity which contracted with [Browns] to perform the services detailed in the Invoices, and the debts have not been sufficiently particularised.
- Straightline Construction was incorporated in March 2020
- Straightline Construction performs civil construction works in metropolitan Melbourne, partiuclarly in Brighton and Clayton
- there are various ‘Straightline’ entities with different controllers, each having its own role in different projects & that Straightline Construction is not involved in the Hansen Yuncken contract at all [38]
- where it is said that Browns had dealings with ‘Straightline’ for several years, it was in fact engaged by four separate Straightline entities depending on the project and the entity involved in the Project was Straightline Civil, not Straightline Construction [40].
- a direction should have been issued to make it clear that invoices were to be issued to Straightline Civil and not Straightline Construction [41] invoices addressed to Straightline Construction should have been requested to be reissued to Straightline Civil.
- on 20 September 2022, Peter Greenstreet, an Operations Manager of Browns, sent an email enquiring as to whom the invoices for the remaining works on the Project should be issued to & Oltan Yemez, representing Straightline Civil, responded, stating that all invoices should be issued to Straightline Civil [42].
- an ASIC search of Straightline Civil records Tarkan Gulenc as the sole director & the correspondence referred to between Mr Gulenc and representatives of Browns confirms that Straightline Civil admits it owes the debt [43]
- in regard to correspondence relied on by Browns to support their proposition that Straightline Construction owes the debt, the reference to intentions to pay does not refer to Straightline Construction being liable to pay the debt [46].
- the communications containing promises to pay in the text message exchanges on 8 July 2022 were in the context of a statutory demand having been served by Browns approximately one month before and no reference to the identity of the contracting party as Straightline Civil [47]
- an agreement has been reached (which he refers to as the ‘Tri-Partite Deed’) between representatives of Hansen Yuncken, Straightline Civil, and Browns in relation to the payment of outstanding amounts, whereby Hansen Yuncken agrees to pay progress payments due to Straightline Civil in respect of the Project directly to Browns, in satisfaction of outstanding invoices rendered by Browns in relation to the Project (including those the subject of the Demand) and that a total of $193,775.56 has been paid to date, being the payment of $105,739.93 (including GST) in relation to the July Payment Schedule and $88,035.63 (including GST) in relation to the August Payment Schedule [51] – [52].
- Staightline Construcion has never been contracted to perform subcontract work on any sites in Hawthorn [12]
The respondent’s evidence Read the rest of this entry »